Glen Elder Dam Spillway

Usbr-project-150-web
Glenelder-project-47
Glenelder-9
Usbr-project-101-web
Usbr-people-402-web
Glenelder-project-36
Usbr-project-105-web
Usbr-project-79-web
Usbr-project-123-web
Glenelder
Glenelder-27

Glen Elder Dam was constructed in the mid-twentieth century as part of a federal campaign to prevent extreme flooding of the Missouri River Basin. The dam in north central Kansas is a source for irrigation and municipal water. It also forms Waconda Lake, a popular recreational destination with 100 miles of shoreline.

With the goal of ensuring that the dam continues to protect and benefit the region, Ames began a three-year project in 2022 to repair the dam’s 644-foot-wide concrete spillway.

Crews are replacing 98 spillway panels, which equates to 13,200 cubic yards of self-batched and placed concrete. Project scope also includes the removal of aging concrete, existing drainage material, and pipe; rock excavation; and pipe trench grading.

In the project’s first year, Ames constructed temporary roads, set up the batch plant, and developed the process to produce a consistent batch of concrete that meets owner requirements. In 2023 and 2024, crews removed existing concrete, placed spillway panels, and installed new piping.

Learn more: Bureau of Reclamation

Markets: Federal, Water Resources, Dams

Location: Glen Elder, Kansas

Completion: November 2025 (anticipated)

Project Owner: U.S. Bureau of Reclamation

Details:

  • 81,912 CY of earthwork
  • 3,230 CY of rock excavation
  • 7,400 LF of HDPE pipe
  • 16,535 CY of concrete production
  • 11,900 CY of concrete removal
  • 1.9 million LBS of rebar